Warning

 

Close
Confirm Action

Are you sure you wish to do this?

Cancel Confirm
AR15.COM
10/20/2010 12:09:08 PM EDT
Putting together a bid for a generator replacement project today.



Boy, did the engineer blow it on his estimate.  His estimated cost was $1.3 million for the generators, including installation.  I just got my quote for the gen sets.  $3.9 million for the 4 of them.  That does not include my labor and materials for the installation.  I have a feeling this bid will not be awarded.
10/20/2010 12:12:08 PM EDT
[#1]
Okay, thanks for sharing.
10/20/2010 12:13:13 PM EDT
[#2]



Quoted:


Okay, thanks for sharing.


You're welcome.



 
10/20/2010 12:14:41 PM EDT
[#3]
Well either he is very far off or you are getting hosed.
10/20/2010 12:14:45 PM EDT
[#4]
Maybe he's got a lead on a truckload of "gray market" generators...
10/20/2010 12:15:37 PM EDT
[#5]
k
10/20/2010 12:16:26 PM EDT
[#6]
It's always the mundane details that get them.




10/20/2010 12:17:51 PM EDT
[#7]
Forgot to multiply by 4?
10/20/2010 12:19:39 PM EDT
[#8]





Quoted:



Forgot to multiply by 4?



I think so.





The generators are $800k each.  Add another $700k for the switchgear to run them.





 
10/20/2010 12:19:42 PM EDT
[#9]

10/20/2010 12:19:58 PM EDT
[#10]
Quoted:
Forgot to multiply by 4?


that would be 5.2 + installation materials but there could be a contractor price difference than a vaca price
10/20/2010 12:21:32 PM EDT
[#11]
Sure they are replacing all 4?

I once asked for a bid on interior demo of a building.  Bid came in at a fraction of my budget.  Turns out the bidder missed the note that said "6 story building - existing floor plan typical for all)
10/20/2010 12:22:35 PM EDT
[#12]



Quoted:


Sure they are replacing all 4?



I once asked for a bid on interior demo of a building.  Bid came in at a fraction of my budget.  Turns out the bidder missed the note that said "6 story building - existing floor plan typical for all)


Yes, they are replacing all 4.



 
10/20/2010 12:23:03 PM EDT
[#13]



Quoted:



Quoted:

Forgot to multiply by 4?




that would be 5.2 + installation materials but there could be a contractor price difference than a vaca price
beat by ~20sec





 
10/20/2010 12:25:16 PM EDT
[#14]
Or perhaps he was lazy and needed a number to put in a cap-ex for the next budget and wantedyou to do the work, so he just pulled something out of his ass, to get a prelimnary to send out RFQ's so they could get back actual numebrs for the next budget...
10/20/2010 12:34:46 PM EDT
[#15]
10/20/2010 12:35:08 PM EDT
[#16]
we dont have those gensets in stock?  oh.
10/20/2010 12:36:15 PM EDT
[#17]



Quoted:


we dont have those gensets in stock?  oh.


Not 1100 kw sets at 5 kv.  These guys have a 7 month lead time.



 
10/20/2010 12:37:52 PM EDT
[#18]
Quoted:

Quoted:
we dont have those gensets in stock?  oh.

Not 1100 kw sets at 5 kv.  These guys have a 7 month lead time.
 


oh shit.  I could have sworn we had those.  So and So said we had em.
10/20/2010 12:38:24 PM EDT
[#19]



Quoted:



Quoted:




Quoted:

we dont have those gensets in stock?  oh.


Not 1100 kw sets at 5 kv.  These guys have a 7 month lead time.

 




oh shit.  I could have sworn we had those.  So and So said we had em.


lol



 
10/20/2010 12:42:01 PM EDT
[#20]



Quoted:





Quoted:


Quoted:




Quoted:

we dont have those gensets in stock?  oh.


Not 1100 kw sets at 5 kv.  These guys have a 7 month lead time.

 




oh shit.  I could have sworn we had those.  So and So said we had em.


lol

 


Is this guy a goner?



 
10/20/2010 12:46:58 PM EDT
[#21]



Quoted:





Quoted:




Quoted:


Quoted:




Quoted:

we dont have those gensets in stock?  oh.


Not 1100 kw sets at 5 kv.  These guys have a 7 month lead time.

 




oh shit.  I could have sworn we had those.  So and So said we had em.


lol

 


Is this guy a goner?

 


I have no idea.  He works for the engineering firm that was contracted by the City to design this system.



 
10/20/2010 12:49:36 PM EDT
[#22]
Quoted:

Quoted:
Okay, thanks for sharing.

You're welcome.
 


10/20/2010 12:53:27 PM EDT
[#23]
Are we talking a mucincipal installation here?



I'm not an estimator nor contractor, but I will say that I have worked with several civil engineers in a municipal setting who couldn't estimate shit from shit.



The best story I have is of a civil engineer EIT who was approached by the city manager and asked to work on a project that included pouring a cement foundation within a large storage shed.  When the work was put out for bid, the 3 cement contractors came out and I had the pleasure of talking with them.



I know very little about the civil/industrial side of things, but one of the rep's from the concrete company walked up to me and asked if I had "engineered" the flooring plan for this building.  I said no and he went on to explain to me that whoever did had so overdone the specs that "you could drive tanks in here and park them if you wanted to".  



The shed was meant for parking snow-blowers and other small equipment.  I had a little LOL when he said that.
10/20/2010 1:03:28 PM EDT
[#24]



Quoted:


Are we talking a mucincipal installation here?



I'm not an estimator nor contractor, but I will say that I have worked with several civil engineers in a municipal setting who couldn't estimate shit from shit.



The best story I have is of a civil engineer EIT who was approached by the city manager and asked to work on a project that included pouring a cement foundation within a large storage shed.  When the work was put out for bid, the 3 cement contractors came out and I had the pleasure of talking with them.



I know very little about the civil/industrial side of things, but one of the rep's from the concrete company walked up to me and asked if I had "engineered" the flooring plan for this building.  I said no and he went on to explain to me that whoever did had so overdone the specs that "you could drive tanks in here and park them if you wanted to".  



The shed was meant for parking snow-blowers and other small equipment.  I had a little LOL when he said that.


Yes, it is a municipal installation.  A waste water treatment plant to be exact.



 
10/20/2010 1:03:41 PM EDT
[#25]
Quoted:

Quoted:
we dont have those gensets in stock?  oh.

Not 1100 kw sets at 5 kv.  These guys have a 7 month lead time.
 


Those are on sale right now at Harbor Freight.  Don't forget the 20% off coupon.
10/20/2010 1:04:53 PM EDT
[#26]



Quoted:



Quoted:




Quoted:

we dont have those gensets in stock?  oh.


Not 1100 kw sets at 5 kv.  These guys have a 7 month lead time.

 




Those are on sale right now at Harbor Freight.  Don't forget the 20% off coupon.


Harbor Freight only has the 1.1 megawatt sets.





 
10/20/2010 1:08:50 PM EDT
[#27]
Quoted:

Quoted:
Quoted:

Quoted:
we dont have those gensets in stock?  oh.

Not 1100 kw sets at 5 kv.  These guys have a 7 month lead time.
 


Those are on sale right now at Harbor Freight.  Don't forget the 20% off coupon.

Harbor Freight only has the 1.1 megawatt sets.

 


I  think Klein Tools makes a decimal adjustor punch set.  You'll be good to go.
10/20/2010 1:09:23 PM EDT
[#28]


that graphic is always showing up in my PM class.
10/20/2010 1:13:10 PM EDT
[#29]
Electrifying tale, bro
10/20/2010 1:33:27 PM EDT
[#30]
Quoted:
Electrifying tale, bro


I'm shocked that the engineer didn't meet with more resistance from the company given the current business climate.

10/20/2010 1:45:24 PM EDT
[#31]
Let's see if I get lucky today.  Final price - $5.9 mil.
10/20/2010 1:49:25 PM EDT
[#32]

I told you that $1.3M was for one fucking generator! Now multiply that by three.

10/20/2010 1:51:09 PM EDT
[#33]
I didn't even want any generators
10/20/2010 3:09:11 PM EDT
[#34]



Quoted:





Quoted:

Are we talking a mucincipal installation here?



I'm not an estimator nor contractor, but I will say that I have worked with several civil engineers in a municipal setting who couldn't estimate shit from shit.



The best story I have is of a civil engineer EIT who was approached by the city manager and asked to work on a project that included pouring a cement foundation within a large storage shed.  When the work was put out for bid, the 3 cement contractors came out and I had the pleasure of talking with them.



I know very little about the civil/industrial side of things, but one of the rep's from the concrete company walked up to me and asked if I had "engineered" the flooring plan for this building.  I said no and he went on to explain to me that whoever did had so overdone the specs that "you could drive tanks in here and park them if you wanted to".  



The shed was meant for parking snow-blowers and other small equipment.  I had a little LOL when he said that.


Yes, it is a municipal installation.  A waste water treatment plant to be exact.

 


For the city of Calgary?  



Calgary (where I live) was/is going to replace all 4 of their gen-set's they currently use.  I believe they were only going to replace the 4 with 3, however, as the generation capacity of the 3 was equal to the 4 they already use.



I have to say, when I first saw those 4 they were using, I was impressed.  I've worked around allot of heavy equipment, but all 4 of those suckers running at the same time was awe inspiring.



Do the gen-sets you install run on natural or digester gas, or both?



I believe the largest plant here generates something like 1/2 the power they use from the digested sludge that the plant generates, which is pretty impressive, because it is a huge facility.



 
10/20/2010 3:10:29 PM EDT
[#35]



Quoted:





Quoted:




Quoted:

Are we talking a mucincipal installation here?



I'm not an estimator nor contractor, but I will say that I have worked with several civil engineers in a municipal setting who couldn't estimate shit from shit.



The best story I have is of a civil engineer EIT who was approached by the city manager and asked to work on a project that included pouring a cement foundation within a large storage shed.  When the work was put out for bid, the 3 cement contractors came out and I had the pleasure of talking with them.



I know very little about the civil/industrial side of things, but one of the rep's from the concrete company walked up to me and asked if I had "engineered" the flooring plan for this building.  I said no and he went on to explain to me that whoever did had so overdone the specs that "you could drive tanks in here and park them if you wanted to".  



The shed was meant for parking snow-blowers and other small equipment.  I had a little LOL when he said that.


Yes, it is a municipal installation.  A waste water treatment plant to be exact.

 


For the city of Calgary?  



Calgary (where I live) was/is going to replace all 4 of their gen-set's they currently use.  I believe they were only going to replace the 4 with 3, however, as the generation capacity of the 3 was equal to the 4 they already use.



I have to say, when I first saw those 4 they were using, I was impressed.  I've worked around allot of heavy equipment, but all 4 of those suckers running at the same time was awe inspiring.



Do the gen-sets you install run on natural or digester gas, or both?



I believe the largest plant here generates something like 1/2 the power they use from the digested sludge that the plant generates, which is pretty impressive, because it is a huge facility.

 


Santa Rosa, California.



And these units are able to run on either natural gas or digester gas.



 
10/20/2010 3:11:55 PM EDT
[#36]
Quoted:
Or perhaps he was lazy and needed a number to put in a cap-ex for the next budget and wantedyou to do the work, so he just pulled something out of his ass, to get a prelimnary to send out RFQ's so they could get back actual numebrs for the next budget...


Why did you say CrapEx.  I HATE that program.  It is a piece of shit built by some guy who must have loved beans and wears a tutu in Texas.
10/20/2010 3:12:15 PM EDT
[#37]





WIN.



 
10/20/2010 3:15:06 PM EDT
[#38]



Quoted:





Quoted:




Quoted:




Quoted:

Are we talking a mucincipal installation here?



I'm not an estimator nor contractor, but I will say that I have worked with several civil engineers in a municipal setting who couldn't estimate shit from shit.



The best story I have is of a civil engineer EIT who was approached by the city manager and asked to work on a project that included pouring a cement foundation within a large storage shed.  When the work was put out for bid, the 3 cement contractors came out and I had the pleasure of talking with them.



I know very little about the civil/industrial side of things, but one of the rep's from the concrete company walked up to me and asked if I had "engineered" the flooring plan for this building.  I said no and he went on to explain to me that whoever did had so overdone the specs that "you could drive tanks in here and park them if you wanted to".  



The shed was meant for parking snow-blowers and other small equipment.  I had a little LOL when he said that.


Yes, it is a municipal installation.  A waste water treatment plant to be exact.

 


For the city of Calgary?  



Calgary (where I live) was/is going to replace all 4 of their gen-set's they currently use.  I believe they were only going to replace the 4 with 3, however, as the generation capacity of the 3 was equal to the 4 they already use.



I have to say, when I first saw those 4 they were using, I was impressed.  I've worked around allot of heavy equipment, but all 4 of those suckers running at the same time was awe inspiring.



Do the gen-sets you install run on natural or digester gas, or both?



I believe the largest plant here generates something like 1/2 the power they use from the digested sludge that the plant generates, which is pretty impressive, because it is a huge facility.

 


Santa Rosa, California.



And these units are able to run on either natural gas or digester gas.

 


2 questions, if you could oblige me:



Typically how long would you get out of a motor of that size.



What would be the horsepower output of the same?  Just a generic number, I don't need specifics.
 
10/20/2010 3:38:44 PM EDT
[#39]
Quoted:
Putting together a bid for a generator replacement project today.

Boy, did the engineer blow it on his estimate.  His estimated cost was $1.3 million for the generators, including installation.  I just got my quote for the gen sets.  $3.9 million for the 4 of them.  That does not include my labor and materials for the installation.  I have a feeling this bid will not be awarded.


7 month lead time? Who you dealing with. $800,000.00 for 1100kw@5kv? You can pick up a CAT 3.1meg @ 12470v for $800,000 NIB.
10/20/2010 4:04:49 PM EDT
[#40]



Quoted:





Quoted:




Quoted:




Quoted:




Quoted:

Are we talking a mucincipal installation here?



I'm not an estimator nor contractor, but I will say that I have worked with several civil engineers in a municipal setting who couldn't estimate shit from shit.



The best story I have is of a civil engineer EIT who was approached by the city manager and asked to work on a project that included pouring a cement foundation within a large storage shed.  When the work was put out for bid, the 3 cement contractors came out and I had the pleasure of talking with them.



I know very little about the civil/industrial side of things, but one of the rep's from the concrete company walked up to me and asked if I had "engineered" the flooring plan for this building.  I said no and he went on to explain to me that whoever did had so overdone the specs that "you could drive tanks in here and park them if you wanted to".  



The shed was meant for parking snow-blowers and other small equipment.  I had a little LOL when he said that.


Yes, it is a municipal installation.  A waste water treatment plant to be exact.

 


For the city of Calgary?  



Calgary (where I live) was/is going to replace all 4 of their gen-set's they currently use.  I believe they were only going to replace the 4 with 3, however, as the generation capacity of the 3 was equal to the 4 they already use.



I have to say, when I first saw those 4 they were using, I was impressed.  I've worked around allot of heavy equipment, but all 4 of those suckers running at the same time was awe inspiring.



Do the gen-sets you install run on natural or digester gas, or both?



I believe the largest plant here generates something like 1/2 the power they use from the digested sludge that the plant generates, which is pretty impressive, because it is a huge facility.

 


Santa Rosa, California.



And these units are able to run on either natural gas or digester gas.

 


2 questions, if you could oblige me:



Typically how long would you get out of a motor of that size.



What would be the horsepower output of the same?  Just a generic number, I don't need specifics.





 


No idea.  We are electrical contractors.



 
10/20/2010 4:06:42 PM EDT
[#41]



Quoted:



Quoted:

Putting together a bid for a generator replacement project today.



Boy, did the engineer blow it on his estimate.  His estimated cost was $1.3 million for the generators, including installation.  I just got my quote for the gen sets.  $3.9 million for the 4 of them.  That does not include my labor and materials for the installation.  I have a feeling this bid will not be awarded.




7 month lead time? Who you dealing with. $800,000.00 for 1100kw@5kv? You can pick up a CAT 3.1meg @ 12470v for $800,000 NIB.http://i55.tinypic.com/keephv.jpg


It's a GE genset.  I don't know where you are, but we also have to deal with a special air quality management district and noise concerns.



 
10/20/2010 4:13:05 PM EDT
[#42]
Quoted:

Quoted:

Quoted:

Quoted:
Quoted:

Quoted:
we dont have those gensets in stock?  oh.

Not 1100 kw sets at 5 kv.  These guys have a 7 month lead time.
 


oh shit.  I could have sworn we had those.  So and So said we had em.

lol
 

Is this guy a goner?
 

I have no idea.  He works for the engineering firm that was contracted by the City to design this system.
 


I'm gonna go with that was his estimate BEFORE change orders
10/20/2010 4:17:24 PM EDT
[#43]
Quoted:
Quoted:
Putting together a bid for a generator replacement project today.

Boy, did the engineer blow it on his estimate.  His estimated cost was $1.3 million for the generators, including installation.  I just got my quote for the gen sets.  $3.9 million for the 4 of them.  That does not include my labor and materials for the installation.  I have a feeling this bid will not be awarded.


7 month lead time? Who you dealing with. $800,000.00 for 1100kw@5kv? You can pick up a CAT 3.1meg @ 12470v for $800,000 NIB.http://i55.tinypic.com/keephv.jpg


NIB.  LOL.
10/20/2010 4:24:23 PM EDT
[#44]
Quoted:

Quoted:
Quoted:
Putting together a bid for a generator replacement project today.

Boy, did the engineer blow it on his estimate.  His estimated cost was $1.3 million for the generators, including installation.  I just got my quote for the gen sets.  $3.9 million for the 4 of them.  That does not include my labor and materials for the installation.  I have a feeling this bid will not be awarded.


7 month lead time? Who you dealing with. $800,000.00 for 1100kw@5kv? You can pick up a CAT 3.1meg @ 12470v for $800,000 NIB.http://i55.tinypic.com/keephv.jpg

It's a GE genset.  I don't know where you are, but we also have to deal with a special air quality management district and noise concerns.
 


which means  "it's a government and they don't give two shits about how much money it costs, they want the very bestest and mostest and expensivest to build their empire.  I mean hell, it's not their money why should they care?"